FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Figure 9-1 Installing a cabinet sealing plate
Step 2 Install another sealing plate for the cabinet rear door in the same way.
----End
Installing 300 mm Wide Air Conditioner Sealing Plates
Step 1 Use two M5x10 tapping screws to secure a 300 mm wide air conditioner sealing plate to a
cabinet.
Figure 9-2 Installing 300 mm wide air conditioner sealing plates
Step 2 Install another sealing plate on the other side of the cabinet in the same way.
----End
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
9 Installing Cabinet Sealing Plates