Step 2 Install the mounting ears delivered with the LAN switch and secure the LAN switch to the
rack rails in the front of the cabinet.
Figure 7-8 Installing a LAN switch
Step 3 Connect the LAN switch power cable to the PDU2000.
----End
Follow-up Procedure
If a 24-port LAN switch is configured, two power modules need to be installed for the LAN
switch onsite. Insert the power modules into the power slots of the 24-port LAN switch, and
tighten the captive screws on the power module panel.
Figure 7-9 Installing the power modules for a 24-port LAN switch
Issue 04 (2017-06-30)
This section describes only the installation method. The actual product appearance prevails.
The positions of power cable ports vary depending on the LAN switch models. Connect the power cable
based on the actual power port of the LAN switch.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
7 Installing Monitoring Devices
128

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents