Figure 3-27 Removing the screws
Step 2 Remove the cabinet from the pallet.
----End
3.3 (Optional) Adjusting IT Cabinet Side Plates
Context
If the IT cabinet is not fully configured with side plates, adjust the side plate positions based
on the side plate labels before installing the IT cabinet, and ensure that plates are installed on
the outer side of end cabinets.
Procedure
Step 1 Install floating nuts.
Step 2 Secure a side plate to the cabinet using four M6 screws and the floating nuts.
Step 3 Install other side plates in the same way.