Unpacking And Acceptance - Huawei FusionModule2000 Installation Manual

Smart modular data center, 2000 mm high cabinets, single-row aisle containment, 380 v
Hide thumbs Also See for FusionModule2000:
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Installation Guide (2000 mm High Cabinets, Single-Row
Aisle Containment, 380 V)
Precautions for Placing
Place cardboard boxes in sequence based on their numbers.
Figure 1-2 Arranging components

1.2 Unpacking and Acceptance

Context
Unpack and inspect all cabinets, mechanical parts, and components. Check that all the items
are intact and comply with the packing list on the presence of both the project supervisor and
customer.
Procedure
Step 1 Unpack the carton labeled "Contain Packing List" and take out the Packing List.
Step 2 Check all items against the Packing List.
Step 3 If an item is incorrect or missing, contact Huawei technical support.
Step 4 If any item is damaged, fill in the Cargo Replacement Application Form and report it.
Issue 04 (2017-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
1 Installation Preparations
2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents