Figure 7-76 Installing a fastener
When securing the water detection cable to the concrete floor, use the cable nail clips delivered with the
cable to secure the cable.
Figure 7-77 Installing a cable nail clip
Step 3 Place the water detection cable onto the fastener, secure the fastener, and keep the water
detection cable in close contact with the floor.
If multiple water detection cables need to be connected in series, connect the male connector of one
cable to the female connector of another.
Figure 7-78 Securing a water detection cable
----End