Mark all four mounting holes where each angle steel bracket contacts the concrete
platform.
Place a wooden block on the top of an expansion bolt, and then knock at the wooden block
using a claw hammer to avoid damaging the expansion bolt.
When you drill a hole using a hammer drill, keep the drill bit perpendicular to the ground
and hold the drill stock firmly with both hands to prevent irregular drilling and damage to
the ground.
If the ground is too hard and smooth for the drill bit to secure its position, use a chisel to
punch a pit before drilling.
Before you hammer an expansion bolt vertically into a mounting hole, clean up dust from
the inside and surrounding of the hole.
Each angle steel bracket must be secured by two mounting holes. Preferentially drill the
outer two mounting holes. If steel bars in a concrete platform block the drill bit, drill the
inner mounting holes.
2.
3.
4.
5.
Issue 02 (2020-01-15)
Figure 4-3 Determining mounting holes for an angle steel bracket
Drill a hole in each mounting hole position using a hammer drill.
Rotate the nut onto the expansion tube to prevent the expansion tube from fluttering.
Hammer the expansion bolt into the hole vertically until the flat washer is flush with the
ground.
Remove the nut, spring washer, and flat washer.