5.
6.
7.
----End
Issue 02 (2020-01-15)
Figure 6-16 Installing the negative battery cable
If there are multiple battery strings, install negative battery cables for the remaining
battery strings in the same way.
Install the positive battery cable.
Figure 6-17 Installing the positive battery cable
If there are multiple battery strings, install positive battery cables for the remaining
battery strings in the same way.