Figure 4-7 Base installation scenario diagram (unit: mm)
(1) Pre-fab. module base
Step 2 Determine the installation position for the first base in the installation area based on the site
space, and draw longitude and latitude reference lines between the first base and other bases.
Lines should be perpendicular or parallel, with an angle of 90 degrees at cross points.
The point where the reference lines intersect is the middle point for installing a pre-fab.
module base.
Step 3 Place bases based on the reference lines.
Issue 02 (2020-01-15)
Copyright © Huawei Technologies Co., Ltd.
(2) Concrete platform
4 Installing Pre-fab. Modules
(3) Ground