Huawei FusionModule1000A20 Installation Manual page 47

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Figure 6-2 Covers position
(1) Supply air vent cover
1.
2.
Issue 02 (2020-01-15)
Use a Phillips screwdriver to remove the screws reserved on the cover of the connection
box from outside of the pre-fab. module.
Figure 6-3 Removing the screws on the cover of the connection box
Cut the glue between the cover and the pre-fab. module using a utility knife.
Copyright © Huawei Technologies Co., Ltd.
6 Installing Devices Inside the Pre-fab. Module
(2) Cable connection box cover
(3) Return air vent cover
41