11 E1/T1 Installation Guide

This section describes the installation and configuration of the E1/T1 interface.
The following topics are described in this section:

11.1 E1/T1 Cable Assembly

11.2 Connecting the E1/T1 Cable to the PIDU Plus
11.3 Testing the E1/T1 Installation
NOTE
The maximum cable length between the ODU and the customers terminating
equipment is 200m (656 feet) for E1/T1.
11.1 E1/T1 Cable Assembly
The E1/T1 cable should be assembled as described in Section 2.10 "Cables and
Connectors".
This procedure applies to the ODU termination, but it must be repeated for the
customer equipment end of the cable when the cable is terminated with an RJ45.

11.1.1 T568B Color Coding

The T568B color coding used in RJ45 E1/T1 cables is illustrated in Figure 118.

Figure 118 - RJ45 Pin Connection (T568B Color Coding)

185