Huawei DBS3900 Installation Manual page 132

Icr dual-mode base station
Hide thumbs Also See for DBS3900:
Table of Contents

Advertisement

DBS3900 (ICR)
Installation Guide
l
Issue 12 (2015-04-30)
Figure 15-20 Installing the +24 V DC input power cable
4.
Route the other end of the power cable along the cable trough at the rear left of the
IFS06. Then connect the power cable to the external power system, as shown in
15-20.
5.
Lay out the cable according to the instructions in
use cable ties to bind the cable.
6.
Label the installed cable according to the instructions in Attaching a Cable-Tying
Label.
To install the 220 V AC input power cable, perform the following operations:
1.
Cut the cable to a length suitable for the actual cable route.
2.
Add an OT terminal to one end of the cable according to the instructions in Assembling
the OT Terminal and the Power Cable.
3.
Connect one end of the power cable to the AC INPUT port on the AC/DC power
system, as shown in
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
15-21.
15 Installing Cables
15.1 Cabling
Requirements, and
Figure
127