Section 7
IEC 61850 communication engineering
94
number of entries in a data set and the number of report control
blocks that can be used.
3.
Add and/or reconfigure default data sets. The 650 series pre-configured IED
includes a number of predefined data sets, but it is possible to add additional
data sets and/or reconfigure default data sets according to the requirements.
Note that reporting data sets shall only contain data intended to
be used by clients, for example for event handling.
4.
Configure report control blocks for each data set used for vertical
communication. The 650 series pre-configured IED includes a number of
predefined report control blocks, but it is possible to add additional control
blocks and/or reconfigure default control blocks according to the requirements.
Up to 8 report clients can be configured.
5.
Connect the report control blocks to vertical IED clients. The report control
blocks are connected to the vertical clients in the SCD file for a 650 series pre-
configured IED. Check each IED client and configure them to the subnetwork
before connecting report control blocks to the clients.
6.
Create a GOOSE message data set for the sending IED. Define the attribute
content of the data set according to the requirements.
The data set for GOOSE may contain signals on data attribute
level or on FCDA level. The latter is also called structured
GOOSE.
Ensure that the same GoID is set for sending and receiving
GOOSE messages.
Note that one data must only be included in one GOOSE data set.
7.
Create the GOOSE control block and connect it to the GOOSE message data
set. Be sure to check the parameters for the GOOSE control block and update
as required.
8.
Connect the GOOSE control block to the client IEDs, subscribing for GOOSE.
9.
Export the updated SCD file.