ABB PQFA Instruction Manual page 89

Power quality filter
Table of Contents

Advertisement

The fault clearance procedure starts with the opening of the power circuit
breaker. The system is reset and the filter conducts again the start-up
sequence as shown hereafter. The fault message can be accessed through
the PQF-Manager.
If within 30 seconds after the re-start of the IGBT' s no critical fault occurs, the
initial fault is cleared and the filter comes back to normal operation.
If a critical fault occurs during those 30 seconds, either it is a different fault
than previously and a new fault clearance procedure is conducted or it is the
same fault.
If it is the same fault, a fault clearance procedure will be re-conducted until the
same fault is detected 5 consecutive times.
In this case, the power breaker is opened, the filter definitively stopped and
the alarm led on the PQF-Manager is lit. The error message can be accessed
through the PQF-Manager.
This procedure is shown in the next page.
Start fan
for 10s
Preload
DC bus
Close MC
Start IGBT
Network
characterisation
Asea Brown Boveri Jumet S.A.
PQFA Instructions Manual
89