Additional requirement
The PG/PC is connected to a switch via the PROFINET interface. The switch is a device in
the PROFINET ring during commissioning.
Installing modules and wiring the assembly
You can set up and wire the hardware before or after configuration and programming of the
user program.
You can find additional information on installation and wiring of an ET 200SP in the
ET 200SP distributed I/O system
(https://support.industry.siemens.com/cs/ww/en/view/58649293) system manual .
The wiring diagram for an ET 200SP for a tunnel section can be found in the section Wiring
diagram for a tunnel section (Page 13).
The procedure for installation and wiring of an S7-1500R/H redundant system is available in
the S7-1500R/H redundant system
(https://support.industry.siemens.com/cs/ww/en/view/109754833) system manual.
Conventions
Steps and settings which are specific for configuration and programming of an S7-1500H
redundant system will be dealt with in detail in the following sections. Procedures which you
are already familiar with from configuring and programming a SIMATIC S7-1500 will only be
briefly outlined.
1.5

Wiring diagram for a tunnel section

Introduction
The figures below show the wiring of the I/O modules of an ET 200SP distributed I/O system
for tunnel section 1 or 3.
When wiring the tunnel section 2, there is no wiring of the digital output modules for the
traffic lights control and barrier control nor of the outdoor light sensor on the analog input
module.
S7-1500R/H redundant system
Getting Started, 10/2018, A5E44910930-AA
Introduction to the example
1.5 Wiring diagram for a tunnel section