Setup the Power Measuring Unit
STEP2
8
Connection method for power and CT.
9
Connection method 
for power and CT.
Tap the "Next" button.
5. Pass the CT Cable through from the Power Measuring Unit until 
sufficient space is available for installation of the main breaker CT.
6. Connect the CT to the three-way split side of the CT Cable.
7. Clamp the CT on the power wire as per the number of current phases 
stated on the CT Cable.
* Ensure that there is no branch wire between the CT measurement point and    
Note
 the power meter, otherwise accurate energy measurement will not be possible.
* The CT cannot provide accurate measurements if the current phase installation 
 positions differ.
* The CT has a polarity. When clamping the CT to the power wire, ensure you   
  follow the direction label on the CT.
* Do not use the CT in a location with wiring temperatures over 50° C.
8. Connect the Power 
Measuring Unit side 
of the CT Cable to
   the CT connector  
labelled MAIN on 
the Power Measur-
ing Unit.
Note
Do not remove 
any other covers.
17
10
Connection method for power 
and CT with solar generation 
and storage battery system.
Installer Tasks
Once the CT cable is 
connected, tapping 
the "Next" button 
displays a screen with 
an option for whether 
a solar generation or 
storage battery 
system is present.
11
Skip to 
 for Yes, 
12
or 
  for No.