In a filter system consisting of more than one unit, the filter with the lowest address will
be considered as the first unit in the chain. The filter with the highest address will be
considered as the last unit in the chain:
In master-slave filter arrangements, it is recommended to assign the lowest
address to the master unit and increment the address by 1 for the next slave etc.
In master-master arrangements, the lowest address must be assigned to the
master unit that is considered as the main controlling unit. When the main master
unit is faulty, the master unit with the next lowest address will become the main
controlling unit.
In order to set the address of each unit in a filter system, the DIP switch module on the
control board has to be set accordingly.
on the control board (Item 22 in the Figure).
17
16
15
14
Figure 71: Location of the filter identification DIP switch on the control board (Item 22)
The filter identification DIP switch consists of 4 switches that can be put in low or high
position (facing the board with the ABB logo at the top left side). The three left hand
DIP switches determine the filter unit address.
that can be chosen and the corresponding configuration to be set.
Figure 71
18
19
13
Manual Power Quality Filter PQFS  Commissioning instructions 143
shows the location of the DIP switch
1
21
20
22
2
12
11
Table 53
shows the filter unit addresses
3
4
5
6
7
8
9
10

Advertisement

Table of Contents
loading

Table of Contents