Overview Of Installation Process; Installation Flow - Huawei Airbridge cBTS3612 Installation Manual

Cdma base station
Hide thumbs Also See for Airbridge cBTS3612:
Table of Contents

Advertisement

Installation Manual
Airbridge cBTS3612 CDMA Base Station
 

1 Overview of Installation Process

This chapter introduces the hardware installation process of BTS in detail. It can be
used as a basic operation specification for cBTS3612 Base Station (shortened as
BTS in the following) hardware installation and commissioning personnel.

1.1 Installation Flow

The hardware installation process is illustrated as follows:
Project information table
Site survey report
Engineering documents
Checklist for installation
environment
Cabling rack, antenna support,
grounding system, and
supporting facilities
Engineering drawings
Layout of the base,
supports and
mounting holes
Installation Process
Start
Project preparations
Project supervisor
Check and verify the installation environment
Project supervisor
Unpack and check goods on the site
Project supervisor/Customer
Are goods
consistent?
Y
Hardware installation
Project supervisor/ third-party engineer
Marking and drilling
Project supervisor/ third-party engineer
Installation of the base, supports and guide rails
Project supervisor/ third-party engineer
Next page
1-1 
1 Overview of Installation Process
Project kickoff agreement
Customer-confirmed
development plan (CCDP)
Packing list
Goods shortage/damage record
N
Project supervisor
Project on-site weekly report
Project on-site routine meeting record
On-site work notification
On-site installation process record
Fasten the nuts
Adjust the levelness
Hardware Installation
Feedback table for
missing goods
Request form for
goods replacement