Installation Manual
Airbridge cBTS3612 CDMA Base Station

3.2.6 Cabinet Installation

Place the upper support (being f i xed already at the lower part of the cabinet upon
delivery) at the lower support and push the cabinet into the lower support and fasten
it with bolts to complete the installation of the cabinet. The process is shown in Figure
3-7.
(1) Bolt M12x30
Figure 3-7 cBTS3612 Cabinet installation on the cement floor

3.3 Installation on Anti-static Floor

Supports of A600 series are adopted for cBTS3612 cabinet installation in the
equipment room with anti-static floor.
(2) Spring washer Ö12
3-8 
Hardware Installation
3 Cabinet Installation
(3) Plain washer Ö12