II. Checking Antenna and Feeder safety measures
1)
The site survey and project design has been finished. Necessary implementation
conditions are ready. Detailed and complete project design documents are
available.
2)
Outdoor construction should be performed in clear weather with no strong wind.
3)
Important safety cautions.
Caution:
Workers on the tower should be secured with safety belts, and workers under the tower should wear
safety helmet. First - aid kits should be available for the work team. The persons working on the tower
should carry handy bandages with themselves in the case of wound and not wear casual clothes or
shoes that are easy to skid.
Remarkable signs should be set up to warn irrelevant personnel away. Persons under
the tower have the responsibility to urge those irrelevant personnel, especially
children, to be away from the site. Tools that are prone to fall down and cause
casualties should be handled with care. Such tools on the tower should be secured
with bolts and kept in proper position. And those tools and metal installation parts not
used temporarily should be kept in tool bags. The tool bags should be sealed after
use and be kept within the reach.

2.7 Unpacking and Checking of Equipment

2.7.1 Verifying the Packing List and Checking the Equipment

I. Checking common goods
The project supervisor and the engineers from the user shall perform this task. First
verify the quantity of equipment against the packing list attached on each package;
then check whether the package is actually addressed to the site and the exterior of
the package is intact. If everything above is perfect, unpack and check the package.
There is a "Packing List" in the package with red label and the project supervisor
should check the goods item by item according the packing list. If any equipment is
found missing, deficient, wrong, extra or damaged upon unpacking and check, stop
unpacking and find out the cause. Then the project supervisor has to fill in the
Equipment Problem Feedback Table and send it timely to the customer service center
of Huawei in the region and the center will handle the problem accordingly.