Unpacking And Checking; Installing The Indoor Unit; Checking The Nitrogen Pressure - Huawei NetCol5000-A050 User Manual

In-row air cooled smart cooling product
Hide thumbs Also See for NetCol5000-A050:
Table of Contents

Advertisement

NetCol5000-A050 In-row Air Cooled Smart Cooling
Product
User Manual (1350 mm Depth)
● The signal cable between the indoor and outdoor units is mandatory if the
outdoor unit is equipped with a temperature control intelligent monitoring
board.
● Shielded cables cannot be used as power cables for outdoor units.

4.3 Unpacking and Checking

Step 1 Check that the external package of the unit is intact. If any damage is found,
notify the carrier immediately.
Step 2 Remove the packing materials. Check whether the exterior of the unit is in good
condition and free of collision marks or scratches. If any damage is found, notify
the carrier immediately.
Step 3 Check the type and quantity of fittings against the packing list. If some fittings are
missing or do not comply with the models in the packing list, record the
information and contact the supplier immediately.
----End

4.4 Installing the Indoor Unit

4.4.1 Checking the Nitrogen Pressure

Step 1 Open the rear door and remove the air filters.
Issue 04 (2022-12-15)
NO TE
The recommended cables are used only when the following requirements are met:
● The cables are routed over a tray or bracket in a single layer.
● The AC voltage loss is less than 3%.
● Single- or multi-core 90°C-resistant copper flexible cables are recommended.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
4 System Installation
63

Advertisement

Table of Contents
loading

This manual is also suitable for:

Netcol5000-a050h4we2Netcol5000- a050h40e2

Table of Contents