Connect Power And Data Cables To Power Bar; Connect Data Cables To The Power Bar; Figure 57: Connections In Power Bar; Table 10: Cable Connection Requirements - NEC LED-FA025i2-220 User Manual

Led wall bundle
Hide thumbs Also See for LED-FA025i2-220:
Table of Contents

Advertisement

6.4

Connect Power and Data Cables to Power Bar

This section is a guide to power and data connection in the Power bar.
Warning!
Only trained personnel, such as electricians or NEC personnel, may
connect the internal power supply to mains power supply.

Table 10: Cable Connection Requirements

No. of People 1
Prerequisites
Cabinets securely installed
Tools
Screwdriver
Equipment
External power cable (not included in delivery)
Data cables from LED Wall to NovaStar Controller (Cat cable, FTP Cat5e)
L
A
N
PE

Figure 57: Connections in Power Bar

A External power input
B Terminal in Power bar
C Network and supply socket in Power bar
6.4.1

Connect Data Cables to the Power Bar

Step 1)
Prepare the data connection according to the cabling plans, see 15.1 Cable Plans.
Each column of cabinets needs one main and one backup data input.
Step 2)
Connect the main data input to the left Ethernet ports and the backup data input to the
right Ethernet ports in the Power bar. See also Figure 57.
B
C
C1
C1 Ethernet port main data
C2 Ethernet port backup data
D1 Data cable main
D2 Data cable backup
L
N
PE
D1
D2
C2
50