24 Introduction to the manual
Quick installation, commissioning and operation flowchart
Plan the installation. Check: ambient conditions, ratings,
required external cooling circuit arrangements, compat-
ibility of the generator, power cable connection, etc.
Select the cables.
Unpack and check the equipment.
Check the type code indicated on the type designation
label against the original order.
Check that all necessary option modules and equipment
are present and correct.
Only intact converters may be started up!
Check the installation site.
Route the cables.
Move the converter to the installation site and attach it
to the floor.
Connect an external cooling circuit to the converter.
Check the insulation of the generator and the generator
cable.
Connect the power cables. Connect the control and the
auxiliary control cables.
Check the installation.
Commission the converter.
Task
Technical data (page 87)
Planning the electrical installation (page 49)
Option manuals (if optional equipment is included)
Checklist before mechanical installation (page 42)
Checklist before mechanical installation (page 42)
Routing the cables (page 56)
Mechanical installation (page 41)
Cooling and heating (page 115)
Checking the insulation of the assembly (page 61)
Electrical installation (page 61)
Installation checklist (page 67)
Firmware manual
See