66 Electrical installation

Connecting the control cables

Control cable terminals for customer connections are located in the auxiliary control cubicle.
For wiring, see the circuit diagrams delivered with the converter.
Control cable terminals for customer connections and lead-throughs in the auxiliary control cubicle
Connector
Description
X1
Customer connection for 400 V AC non-UPS auxiliary power supply
X2
Customer connection for 230 V AC UPS auxiliary power supply
X3.1
Customer connection for Ethernet
X3.2
Master-slave Ethernet connection
X5
Customer connection for I/O
PROFIBUS: Customer connects it to the FPBA-01 adapter module.

Default I/O connection diagrams