Completing The Test; Voltage Protection; Two Step Undervoltage Protection Uv2Ptuv; Verifying The Settings - ABB rec670 Commissioning Manual

Intelligent electronic device
Hide thumbs Also See for rec670:
Table of Contents

Advertisement

Section 10
Testing functionality by secondary injection
10.4.16.2
10.5
10.5.1
10.5.1.1
118

Completing the test

Continue to test another function or end the test by changing the TestMode setting to
Off. Restore connections and settings to their original values, if they were changed for
testing purposes.

Voltage protection

Two step undervoltage protection UV2PTUV

Prepare the IED for verification of settings outlined in section
verify
settings".

Verifying the settings

Verification of START value and time delay to operate for Step 1
1.
Check that the IED settings are appropriate, especially the START value, the
definite time delay and the 1 out of 3 operation mode.
2.
Supply the IED with three-phase voltages at their rated values.
3.
Slowly decrease the voltage in one of the phases, until the START signal
appears.
4.
Note the operate value and compare it with the set value.
The operate value in secondary volts is calculated according to
the following equations:
For phase-to-earth measurement:
U
UBase VT
1
sec
<
×
×
100
VTprim
3
IECEQUATION2430 V1 EN
For phase-to-phase measurement:
U
1
VT
sec
<
UBase
×
×
100
VTprim
IECEQUATION2431 V1 EN
5.
Increase the measured voltage to rated load conditions.
6.
Check that the START signal resets.
7.
Instantaneously decrease the voltage in one phase to a value about 20% lower
than the measured operate value.
8.
Measure the time delay for the TRIP signal, and compare it with the set value.
9.
Check the inverse time delay by injecting a voltage corresponding to 0.8 × U1<.
1MRK 511 360-UEN A
"Preparing the IED to
(Equation 20)
(Equation 21)
Bay control REC670 2.1 IEC
Commissioning manual

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 seriesRelion rec670

Table of Contents