Visual Inspection; Maintenance Tests; Preparation - ABB rec670 Commissioning Manual

Intelligent electronic device
Hide thumbs Also See for rec670:
Table of Contents

Advertisement

Section 12
Commissioning and maintenance of the fault clearing system
12.2.1
12.2.2
12.2.2.1
198
Every four to six years
Periodic maintenance test for protection IEDs of objects with redundant
protection system.
First maintenance test should always be carried out after the first half
year of service.
When protection IEDs are combined with built-in control, the test
interval can be increased drastically, up to for instance 15 years,
because the IED continuously reads service values, operates the
breakers, and so on.

Visual inspection

Prior to testing, the protection IEDs should be inspected to detect any visible damage
that may have occurred (for example, dirt or moisture deposits, overheating).
Make sure that all IEDs are equipped with covers.

Maintenance tests

To be made after the first half year of service, then with the cycle as proposed above
and after any suspected maloperation or change of the IED setting.
Testing of protection IEDs shall preferably be made with the primary circuit de-
energized. The IED cannot protect the circuit during testing. Trained personnel may
test one IED at a time on live circuits where redundant protection is installed and de-
energization of the primary circuit is not allowed.
ABB protection IEDs are preferably tested by aid of components from the
COMBITEST testing system described in information B03-9510 E. Main
components are RTXP 8/18/24 test switch usually located to the left in each protection
IED and RTXH 8/18/24 test handle, which is inserted in test switch at secondary
testing. All necessary operations such as opening of trip circuits, short-circuiting of
current circuits and opening of voltage circuits are automatically performed in the
right order to allow for simple and safe secondary testing even with the object in
service.

Preparation

Before starting maintenance testing, the test engineers should scrutinize applicable
circuit diagrams and have the following documentation available:
1MRK 511 360-UEN A
Bay control REC670 2.1 IEC
Commissioning manual