1MRK 511 360-UEN A
10.6.4.2
Bay control REC670 2.1 IEC
Commissioning manual
Testing functionality by secondary injection
Verification of generator start and stop logic
1.
Ensure that the settings in the IED are appropriate to the default settings,
especially the CurrStartLevel, FreqHighLimit, FreqLowLimit, UHighLimit and
ULowLimit.
2.
Ensure that the setting CBCheck is enabled.
3.
Supply the IED with three-phase currents and voltages at their rated values.
4.
Slowly decrease the frequency of the applied voltage until the START signal
appears.
5.
Activate the CBOPEN input signal.
6.
Slowly decrease the injected current below the CurrStartLevel value until the
START signal disappears.
7.
Compare the current magnitude value to the set value.
Verification of voltage band limit check logic
1.
Ensure that the settings in the IED are appropriate to the default settings,
especially the CurrStartLevel, FreqHighLimit, FreqLowLimit, UHighLimit and
ULowLimit settings.
2.
Ensure that the EnaVoltCheck is enabled.
3.
Supply the IED with three-phase currents and voltages at their rated values.
4.
Check that the VOLTOK signal appears.
5.
Slowly decrease the frequency of the applied voltage until the START signal
appears.
6.
Slowly decrease the positive-sequence voltage of the injected voltage below the
ULowLimit value until the START signal disappears.
7.
Check that the VOLTOK signal disappears.
8.
Compare the reset value to the set voltage low limit value.
9.
Readjust the positive-sequence voltage of the applied voltage to a value within
the set voltage band limits.
10. Check that the START signal reappears.
11. Slowly increase the positive-sequence voltage of the injected voltage above the
UHighLimit value until the START signal disappears.
12. Compare the reset value to the set voltage high limit value.

Completing the test

Continue to test another function or end the test by changing the Test mode setting
to off.
Restore connections and settings to their original values if they were changed for
testing purposes.