Installation And Commissioning Flowchart - ABB ACS800 Hardware Manual

Hide thumbs Also See for ACS800:
Table of Contents

Advertisement

16

Installation and Commissioning Flowchart

Identify the frame size of your drive: R7 or R8.
Plan the installation.
Check the ambient conditions, ratings, required
cooling air flow, input power connection,
compatibility of the motor, motor connection, and
other technical data.
Select the cables.
Unpack and check the unit.
Check that all necessary optional modules and
equipment are present and correct.
Only intact units may be started up.
Check the installation site.
If the drive is about to be connected to an IT
(ungrounded) system, check that the drive is not
equipped with EMC filter +E202.
Route the cables.
Check the insulation of the motor and the motor
cable.
Install the drive. Connect the power cables. Connect
the control and the auxiliary control cables.
Check the installation.
Commission the drive.
Commission the optional brake chopper (if present).
About this Manual
Task
See
"Technical Data / NEMA Ratings"
"Technical Data"
"Planning the Electrical Installation"
Option manual (if optional equipment is
included)
"Mechanical Installation: Moving the Unit,
Before Installation"
If the converter has been non-operational for
more than one year, the converter DC link
capacitors need to be reformed. Ask ABB for
instructions.
"Mechanical Installation: Before Installation"
"Technical Data"
"The ACS800-PC: Type Code." For
instructions on how to disconnect the EMC
filtering, contact ABB.
"Planning the Electrical Installation: Routing
the Cables"
"Electrical Installation: Checking the Insulation
of the Assembly "
"Mechanical Installation, Electrical Installation,
Resistor Braking" (optional)
"Installation Checklist and Start-Up"
"Installation Checklist and Start-Up",
appropriate firmware manual
"Resistor Braking"