Assigning Actions To The Added Sequence Steps; Editing Start Sequence - ABB COM600 series User Configuration Manual

Substation management units 5.1 sequence control
Hide thumbs Also See for COM600 series:
Table of Contents

Advertisement

4.9.
4.9.1.
30
COM600 series 5.1
Sequence Control Configuration Manual
Figure 4.8-2 Device view for a four step sequence showing action and transition objects

Assigning actions to the added sequence steps

Editing start sequence

To edit the start sequence:
1. Double-click the added POU in the Device view to launch the program editor for
the PLC Program. The default view for the Sequence POU in the program editor is
shown in Figure 4.9.1-1.
1MRS755001
four_step_sequence.png

Advertisement

Table of Contents
loading

Table of Contents