3.2 TRANSPORTATION AND INSTALLATION
Table 8 How to Transport and Install the System
Transportation
Transport unit with a forklift.
!
NOTE: Do not transport in a horizontal position. Cabinets should be
maintained upright within +/- 15° of the vertical during handling.
NOTE
3.3 HANDLING
The UPS is shipped in export packaging. Remove the UPS from the package only when it is
ready for installation.
1100B SERIES UPS
OWNERS / TECHNICAL MANUAL
Pull out the UPS cabinet as shown in Figure 32.
Fix the UPS unit in place using the four (4) leveling feet.
Using the two (2) brackets (with pre-drilled hole (0.47"
diameter)), anchor the UPS using the appropriate
hardware (not provided).
MITSUBISHI ELECTRIC 1100B SERIES UPS
Page Number:
3-2
Installation