Installation checklist
Contents of this chapter
This chapter contains an installation checklist which you must complete before
commissioning can take place.
Safety
DANGER
High voltage!
Obey the instructions in chapter
or damage to the equipment can occur.
Before starting to work on the bypass unit, make sure:
•
that the main and auxiliary power supply to the bypass unit is switched off, locked
out, and tagged out
•
that the bypass unit is dead
•
that safety ground connections are in place
•
that personal protective equipment is provided and used when required
•
that everyone involved is informed.
Before energizing the bypass unit, make sure:
•
that all foreign objects are removed from the bypass unit
•
that all internal and external covers are securely fastened and all doors are closed,
locked and / or bolted
•
that the release dials of safety switches are in the locked position.