36 Installation checklist
WARNING! Obey the instructions in chapter
them, injury or death, or damage to the equipment can occur.

Checklist

Do the steps in section
work. Go through the checklist together with another person.
Mechanical installation
1.
Cover of operation interlocking device is fastened properly
2.
All the input/output power cable and PE cable are in bypass cabinet
3.
PE busbar and PE cable is connected properly between drive and bypass cabinet
4.
Ambient operating conditions meet the specifications given in chapter
5.
Drive installed according to the instructions in this manual (Chapters
and
Electrical
installation)
6.
Bypass-drive system securely fastened to the floor
7.
Visual inspection:
no badly affixed or damaged components
no foreign objects inside cabinet
no dirt, dust and humidity inside cabinet
Electrical installation
1.
Types and cross-sections of control cables suitable for the signal type and signal level
2.
Types and cross-sections of power cables selected according to the
Guideline
3.
Cable entry made according to the instructions (Chapter
hardware manual (2UBB004520)
4.
All control cable screens and conductors are connected according to the instructions (Chapter
Electrical
installation) in ACS580MV hardware manual (2UBB004520), appropriately labeled,
and the customer-side connections are completed
Precautions before electrical work
Safety
instructions. If you ignore
on page
11
before you start the
Technical data
Mechanical installation
ACS580MV Engineering
Electrical
installation)
in ACS580MV