8-5-18
Column Cover Assembly replacement
8-5-18-1
Manpower
One person, 15 minutes.
8-5-18-2
Tools
For tools needed, refer to:
Flexible shaft bit driver extension (optional)
8-5-18-3
Preparations
When preparing for the replacement, you must perform the following steps:
1.) Power down the system
2.) Disconnect the mains power cable from the wall outlet.
3.) Disconnect all Probes and External I/O Cabling.
4.) Remove the Side Covers.
5.) Remove the Top Cover.
Follow these links if you need more information:
4-2-3 "Power shut down" on page 4-7.
8-5-2 "Side Covers replacement" on page 8-30.
8-5-4 "Top Cover replacement" on page 8-38.
8-5-18-4
Column Cover Assembly removal
1.) Lower the console to lowest possible level.
2.) Remove the lower screw on the right side that is visible near the rear of the DVD drive.
Figure 8-29 With console lowered, lower right side screw placement
. 2
EV
8-2-5 "Tools needed for servicing the LOGIQ E9" on page
Chapter 8 Replacement procedures
LOGIQ E9 S
M
ERVICE
ANUAL
8-5.
8 - 73

Advertisement

Table of Contents
loading

Table of Contents