No.F005 Fire Extinguishing System Onsite Wiring Diagram
Horn Strobes -2
Horn Strobes -1
Terminal Resistor
red
10K
black
- + +
- + +
Outdoor horn strobe cable connection:
Connect the two black cables to the leftmost binding post, and connect the two
red cables to the rest two binding posts respectively.
CT Rack
0KW
CT Rack
CT Rack
4KW
4KW
4KW
4KW
4KW
4KW
4KW
4KW
EXIT
E
Electrical actuator onsite installation Align the
electrical actuator and the container valve, and
tighten the electrical actuator clockwise.
E
1: Primary power 2: Battery 3: Display panel
The batteries of the extinguishant control panel are installed and delivered according to the picture.
Check that batteries are intact and free of leakage onsite, remove foam, and connect cables.
EXIT
CT Rack
0KW
CT Rack
2
Abort
B
0KW
2 2 2 2
0KW
0KW
0KW
P
D
1.
Extinguishant control panel: Connect cables for extinguishant control panel batteries onsite.
2.
Horn strobe: Install the external horn strobe onsite. Install the base. Apply glue to the cable inlet to
prevent water entry during transportation.
3.
Fire cylinder: Connect cables to the electrical actuator, bind the electrical actuator to the cable tray,
and install the fire cylinder onsite.