Figure 4-45 Removing the protective cover
Step 5 Use a Phillips screwdriver to remove the four screws from the front of the electric
control box, pull the electric control box out along the guide rails by the handle,
and remove the electric control box.
Figure 4-46 Removing the electric control box
Step 6 Replace the electric control box.
Ensure that the four screws are tightened when installing the electric control box.
Step 7 Place a new electric control box and the protective cover in the installation
position and tighten them.
Step 8 Reconnect cables and terminals.
Issue 01 (2021-04-20)
NO TICE
Copyright © Huawei Technologies Co., Ltd.
4 Parts Replacement
101

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents