5.
Step 9 Remove the smart cooling product cables.
1. Before replacing cables, record the cable routes to ensure that the cable routes
are the same before and after the replacement.
2. Pull removed cables completely out of the smart cooling product indoor unit to
facilitate smart cooling product replacement.
1.
Issue 01 (2021-04-20)
Figure 4-7 Removing air filters
Remove the front door and hinge bases from smart cooling product C1.
NO TICE
Use a Phillips screwdriver to remove the active and standby input power
cables for the smart cooling product indoor unit from ports AC1 and AC2 on
the smart cooling product PDB, and remove the corresponding cables from
the integrated UPS circuit breaker.
Copyright © Huawei Technologies Co., Ltd.