Commissioning; Overview Of Commissioning - ABB AccessControl System Manual

Table of Contents

Advertisement

3

Commissioning

3.1

Overview of commissioning

During commissioning it is differentiated between the commissioning of the system devices
("Smart Access Point Pro", "RF/IP Gateway" and "RF Repeater") and the adding and
commissioning of "Electronic cylindrical lock".
If the "Smart Access Point Pro" or the building structure already exists, e.g. in a "ABB-Welcome
IP" system, this part of commissioning is dropped. The same applies when a device is not
required in the planned system. The further steps can be carried out directly in the management
software of the "Smart Access Point Pro".
Step 1
Initial
commissioning of
"Smart Access
Point Pro"
Step 2
Creating the
building structure
Step 3
Placing of "Smart
Access Point Pro"
Step 4
Commissioning of
"RF/IP Gateway"
Step 5
Commissioning of
"RF Repeater"
Step 6
Adding "Electronic
cylindrical lock"
System Manual 2CKA001473B5074
see chapter 3.1.4 "Commissioning the "Smart Access Point"" on page 36
see chapter 5.2 "Building structure" on page 95
Placing the "Smart Access Point Pro" in building structure of the
management software:
– see chapter 5.4.1 "Placing the "Smart Access Point Pro"" on page
114
Commissioning the "RF/IP Gateway" in the management software of
the "Smart Access Point Pro":
– see chapter 3.2.3 ""RF/IP Gateway"" on page 55
Commissioning the "RF Repeater" in the management software of the
"Smart Access Point Pro":
– see chapter 3.2.4 ""RF Repeater"" on page 56
Commissioning the "Electronic cylindrical lock":
– see chapter 3.2.1 ""Electronic cylindrical lock"" on page 51
– The "Electronic cylindrical lock" is already mounted: see chapter
5.3.2 "Add "Electronic cylindrical lock"" on page 105
– "Electronic cylindrical lock" is not yet mounted: see chapter
3.2.2 "Adding larger projects / devices in advance" on page 55
Commissioning
│31