5.6 Connecting AC Input Power Cable 2

Context
You need to prepare M8 OT terminals.
Procedure
Step 1 Remove the waterproof connector from AC OUTPUT2.
Step 2 Route the AC input power cable through the prepared cable routing pipe.
Step 3 Route the AC input power cable and cable routing pipe through the AC OUTPUT2 hole.
Step 4 Remove the insulation layer of the AC input power cable by an appropriate length using a
wire stripper.
Figure 5-8 Peeling a cable
Step 5 Insert each exposed core wire into the crimping area of an OT terminal and crimp them using
hydraulic pliers.
Step 6 Wrap the wire crimping area with heat shrink tubing or PVC insulation tape.
Step 7 Connect the AC input power cable to the AC input terminal block, and then secure them to a
torque of 8 N· m using a 13 mm (0.51 in.) socket wrench with an extension rod.
Issue 01 (2016-12-15)
If heat shrink tubing is used, put it over the cable and then crimp the OT terminal. Blow the heat shrink
tubing using a heat gun until the tubing closely wraps the wire crimping area of the OT terminal. When
using the heat gun, protect devices from being scorched.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.