Before maintaining the ACBox2000, power it off. For details, see
ACBox2000.
Ensure that the AC circuit breaker between the ACBox2000 and the box-type transformer
is OFF. Place a warning sign at the AC circuit breaker to avoid incidents caused by
switch-on of the circuit breaker.
Ensure that all DC switches of the two inverters that connect to the ACBox2000 are OFF.
Table 7-1 Maintenance list
Item
System
running
status
Cable
connectio
ns
Groundin
g
reliability
Issue 01 (2016-12-15)
7
Check Method
Check that the ACBox2000 is not damaged or
deformed.
Check that the ACBox2000 does not generate
abnormal sound when it is in operation.
Check that cables are securely connected.
Check that cables are intact, in particular, the
parts touching the metallic surface are not
scratched.
Check that ground cables are securely connected.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Routine Maintenance

6.3 Powering Off the
7 Routine Maintenance
Maintenance
Interval
Semiannual
The first inspection is
half a year after the
initial commissioning.
From then on, the
interval can be
semiannual or annual.
The first inspection is
half a year after the
initial commissioning.
From then on, the
interval can be
semiannual or annual.