System Commissioning; Checking Before Power-On - Huawei ACBox2000-21-D0-A-US User Manual

Table of Contents

Advertisement

ACBox2000-21-D0-A-US
User Manual (U.S. Edition)

6.1 Checking Before Power-On

Table 6-1 Checking Before Power-On
No.
1
2
3
4
5
6
7
8
9
10
11
Issue 01 (2016-12-15)
6
Check That
The ACBox2000 is installed reliably in position.
All ground cables are connected securely and reliably.
All AC input power cables are connected correctly, securely,
and reliably. Phase cables L1, L2, and L3 are connected
correctly.
All AC output power cables are connected correctly,
securely, and reliably. Phase cables L1, L2, and L3 are
connected correctly.
The insulation partitions and safety warning panels are
installed reliably in position.
No foreign matter is left inside the ACBox2000.
No insulation layer is damaged and no metal is exposed.
All cables are bound neatly, and cable ties are secured
evenly and properly in the same direction.
There is no unnecessary adhesive tape or cable ties on
cables.
Check that all used waterproof connectors at the chassis
bottom are applied with firestop putty and all locking caps
are tightened.
Check that all the locking caps on idle waterproof
connectors at the chassis bottom are tightened.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

System Commissioning

6 System Commissioning
Check Result
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
□ Yes □ No
35