Huawei LUNA2000-100KTL-M1 User Manual page 74

Smart power control system
Hide thumbs Also See for LUNA2000-100KTL-M1:
Table of Contents

Advertisement

LUNA2000-100KTL-M1 Smart Power Control System
User Manual
Step 2 Upgrade software of the new Smart PCS. Ensure that the software version of the
new Smart PCS is the same as that of other Smart PCSs on site.
Step 3 Choose Monitoring > Running Param. > Grid Parameters, and set Grid code.
Ensure that the grid code setting of the new Smart PCS matches the local grid
code. Wait for 10s, and then go to step 4.
Step 4 The settings of Grid Parameters, Protection Parameters, Feature Parameters,
Power Adjustment, and Power Baseline of the new device must be synchronized
from other devices. This section uses Grid Parameters settings as an example to
describe how to synchronize data. The operations for setting other parameters are
similar.
Click Monitoring, select a running device, choose Running Param. > Grid
Parameters > All > Batch configurations, and click Confirm to synchronize data
to the new device.
Figure 8-19 Setting running parameters
Step 5 Click Monitoring.
1.
2.
Issue 07 (2023-07-15)
Select the faulty Smart PCS, choose Running Param. > Adjustment, and
record the values of Adjust total energy yield and Calibration of total
power supply from grid.
Select the new device, choose Running Param. > Adjustment, and set Adjust
total energy yield and Calibration of total power supply from grid to be
the same as those of the original device.
Copyright © Huawei Technologies Co., Ltd.