11.8.2.5

Checking the operation of the dv/dt and di/dt based function

Check the operation of the dv/dt and di/dt based function if included in the IED.
1.
Simulate normal operating conditions with the three-phase currents in phase with their
corresponding phase voltages and with all of them equal to their rated values.
2.
Change the voltages and currents in all three phases simultaneously.
The voltage change must be higher than the set value DVPU and the current change must be lower
than the set value DIPU.
3.
Apply normal conditions as in step 1.
The BLKV, BLKZ and 3PH signals should reset, if activated, see step
4.
Change the voltages and currents in all three phases simultaneously.
The voltage change must be higher than the set value DVPU and the current change must be
higher than the set value DIPU.
The BLKV, BLKZ and 3PH signals should not appear.
5.
Repeat step 2.
6.
Connect the nominal voltages in all three phases and feed a current below the trip level in all three
phases.
7.
Keep the current constant. Disconnect the voltage in all three phases simultaneously.
The BLKV, BLKZ and 3PH signals should not appear.
8.
Change the magnitude of the voltage and current for phase 1 to a value higher than the set value
DVPU and DIPU.
9.
Check that the pickup output signals PU_DV_A and PU_DI_A and the general pickup signals
PU_DV or PU_DI are activated.
10.
Check that the pickup output signals for the current and voltage phases 2 and 3 are activated by
changing the magnitude of the voltage and current for phases 2 and 3.
11.8.2.6

Completing the test

Continue to test another function or end the test by changing the TESTMODE setting to Disabled.
Restore connections and settings to the original values, if changed for testing purposes.
11.8.3

Voltage based delta supervision DELVSPVC

Prepare the IED for verification of settings outlined in Section
11.8.3.1

Verifying the signals and settings

Make sure that the function is connected to SMAI function with V3P signal.
Delta supervision function has 6 different modes of operation. Proceed as follows to test the function in a
particular mode.
1.
Set the following parameters:
132
The BLKV and BLKZ signals appear without any time delay. The BLKZ signal will be
activated only if the internal deadline detection is not activated at the same time.
3PH should appear after 5 seconds, if the remaining voltage levels are lower than the set
VDLDPU of the dead line detection function.
© 2017 - 2022 Hitachi Energy. All rights reserved
1MRK 511 409-UUS Rev. K
1
and 2.
GUID-FBFEC9C5-1B76-4688-A00D-9EEB33326966 v1
"Preparing the IED to verify
GUID-B05EE7E5-2360-4036-991A-00747C47A625 v2
Phasor measurement unit RES670
Commissioning manual
M1405-96 v12
M1405-130 v5
settings".

Advertisement

Table of Contents
loading

This manual is also suitable for:

Relion 670 series

Table of Contents