Hitachi Relion RES670 Commissioning Manual page 83

Phasor measurement unit
Hide thumbs Also See for Relion RES670:
Table of Contents

Advertisement

1MRK 511 409-UUS Rev. K
IEC15000024 V1 EN-US
The Signal Monitoring menu changes and indicates the forcing values that can be edited.
IEC15000025 V1 EN-US
5.
Select and edit the values.
6.
Click Acknowledge and send.
IEC15000026 V1 EN-US
This commits the values to the IED and exits the editing session.
7.
Click Cancel to abort the changes and revert back to actual IED values.
IEC15000032 V1 EN-US
To force more signals, click the button Start editing signal value for forcing again.
Phasor measurement unit RES670
Commissioning manual
Regardless if the forcing changes are commited or canceled, the forcing is still active.
© 2017 - 2022 Hitachi Energy. All rights reserved
Section 10
Testing IED operation
77