Figure 7-3 Starting a capacity test
----End

7.3.2 Downloading the Test Data

Procedure
Step 1 On the WebUI, choose Query > Battery Test Records, choose logs that need to be
queried from the Log drop-down list box, and click Query.
Figure 7-4 Battery Test Records
Step 2 Choose logs that have been queried from the Log drop-down list box, and click
Export.
----End
Issue 02 (2024-01-05)
NO TE
The capacity test automatically stops in any of the following cases:
● The battery discharge voltage reaches the EOD voltage plus 0.01 V.
● The load fluctuation exceeds 10%.
● An alarm is generated.
When the battery discharge voltage reaches the EOD voltage plus 0.01 V, the test is
complete. The test data is obtained from the capacity test. Based on monthly capacity test
data, select the test data obtained from a capacity test that has the maximum discharge
capacity as the current-month test data. Save the test data obtained from the latest 36
tests.
NO TE
If the UPS does not communicate with SmartLi 3.0, batteries are managed as lead-acid
batteries by default and the battery information is subject to the data displayed on the
SmartLi or NMS.
Copyright © Huawei Digital Power Technologies Co., Ltd.
7 Routine Maintenance