UPS5000-H-600 kVA-FT(M)
User Manual (FusionPower6000)

4.5 Sealing Cabinets

● If the equipment will not be powered on after installation, take dustproof
● After the installation is complete, take anti-condensation measures and keep
● Use the sealing putty delivered with the equipment to seal the cabinet.
● Do not remove the transparent film.
Step 1 Ensure that all items have been checked after the installation.
Step 2 Fill in gaps between the cables and the cabinets with sealing putty.
1.
2.
Figure 4-3 Filling a gap with sealing putty
(1) Paper protective film
Step 3 Reinstall all covers.
Step 4 Close the cabinet doors.
Issue 02 (2024-01-05)
CA UTION
measures (for example, use a dust cover) to prevent equipment damage due to
dust buildup inside it. Remove the dust cover only when the equipment is ready
for operation.
the air conditioner running. Do not store the equipment in an environment
where the temperature and humidity are uncontrollable for a long period of
time. Otherwise, the equipment may be damaged due to condensation.
Remove the paper protective film from the sealing putty and keep the
transparent film.
Fill the gaps between the cables and the cabinets with the sealing putty.
Ensure that the transparent film faces upward.
Copyright © Huawei Digital Power Technologies Co., Ltd.
(2) Transparent film
4 Installation
(3) Sealing putty (with the
transparent film facing
upward)
70