Electrical Installation; Commissioning; Connections - ABB PowerValue 11/31 T Operating Manual

10 kva, 10 kva b, 10 kva b2, 10 kva s, 20 kva, 20 kva b, 20 kva s
Hide thumbs Also See for PowerValue 11/31 T:
Table of Contents

Advertisement

4.2 Electrical Installation

4.2.1

Commissioning

The UPS must be commissioned by a fully trained and authorized field service engineer before being
put into use. The commissioning of the UPS involves the connection of the UPS and batteries, the
verification of the electrical installation and operating environment of the UPS, the controlled start-up
and testing of the UPS and customer training.
TO ENSURE CORRECT OPERATION OF THE UPS AND BATTERIES, IT IS
NECESSARY TO PROVIDE THE MAINS CABLES WITH APPROPRIATE FUSE
PROTECTION
CAUTION!
4.2.2

Connections

Before installing the electrical wiring, check the nominal amperage of your incoming feeder.
DANGER!
THE CABLING CONNECTIONS MUST BE CARRIED OUT BY QUALIFIED
ELECTRICAL PERSONNEL
WARNING!
DO NOT USE THE WALL SOCKET AS THE INPUT POWER SOURCE FOR
THE UPS. ITS RATED CURRENT IS NOT ADEQUATE TO THE FEED THE UPS
AND MAY BURN THE SOCKET
CAUTION!
Modifications reserved
Page 18/49
The UPS is cabled through the terminal blocks as indicated in
Figure 6: Terminal blocks