PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
Figure 7-12 Installing alarm cables for the isolation transformer
Step 2 Install AC power cables between the SUN2000-150KTL-S0 and the isolation transformer.
The AC input neutral wire of the isolation transformer must not be grounded.
Issue 03 (2020-04-10)
In this example, alarm cables are installed for an 80 kVA isolation transformer.
Copyright © Huawei Technologies Co., Ltd.
7 Installing Cables