Commissioning Air Cooled Smart Cooling Products - Huawei FusionModule1000A40 Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A40:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
Port Name
(6) RST
(7) SD
(8) SW1–4
Procedure
Step 1 Check the alarm indicator. If an alarm is displayed, clear the alarm.
Step 2 Verify the MDU configurations based on the integrated UPS user manual.
During the MDU power-on commissioning, you are not allowed to modify the MDU initial
configurations unless you are authorized by onsite Huawei engineers.
Step 3 Enter a user name and password to access the MDU, set the user name, password, time, and
language, and check that the initial parameter settings are correct.
----End

8.2 Commissioning Air Cooled Smart Cooling Products

Prerequisites
The power-on commissioning for the upstream PDC of air cooled smart cooling products is
completed.
Issue 04 (2020-01-17)
Port Description
Insert the USB flash drive, import
and export the configuration file,
export run logs, and upgrade
software.
Reset the MDU.
SD card slot
DIP switch
The ports are protected by a security mechanism.
For the setting method, see the integrated UPS user manual.
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components
Remarks
N/A
N/A
N/A
51