Moving Heavy Objects
Wear protective gloves to protect hands when moving heavy objects.

2.5 Laying Out Cables

Binding Signal Cables
Signal cables must be bound separately from strong-current cables and high-voltage cables.
Laying Out Power Cables
When the temperature is very low, violent impact or vibration may damage the power cable
sheathing. To ensure safety, comply with the following requirements:
Issue 03 (2018-01-25)
Be careful to prevent injury when moving heavy objects.
It is recommended that tools such as a pallet truck be used to transport the heavy PDC.
Power cables should be laid out or installed only when the temperature is higher than
0° C.
Store power cables for at least 24 hours at room temperature before laying out them if
they were previously stored at sub-0º C.
Handle power cables with caution, especially at a low temperature. Do not drop the
power cables directly from the vehicle.