Installation procedure
Mount the server to a rack in the following procedure. Always install the server with two or more persons.
1.
Pull the slide rails from left and right outer rails until
they are locked.
2.
With two or more persons, firmly hold the
server and mount it to the rack.
3.
When the server is pushed into the rack and
is locked, push the server to the end while
pulling the release levers (blue) on both
sides of the server.
4.
Push the server until its lock on front panel
clicks.
138
Note
Make sure that locking mechanism work normally.