4.3.5 Installing the Battery in the Fire Control Panel

Prerequisites
Procedure
Step 1 Open the fire control panel and remove the cover.
Step 2 Install the battery and cover in the fire control panel.
Step 3 Connect battery cables to the fire control panel.
Issue 02 (2021-11-15)
CA UTION
If a battery is damaged, contact your local office.
In an outdoor scenario, you are advised to power on the fire control panel
within 24 hours after unpacking. Otherwise, place it in a dry indoor
environment without corrosive gas.
Determine the position of the fire control panel.
Figure 4-16 Position of the fire control panel
CA UTION
Do not damage components in the fire control panel during the installation.
NO TE
To verify that the battery connection of the fire control panel works properly, perform the
following steps:
1. Turn on the battery switch of the fire control panel and keep it running using the
battery power supply.
2. Turn off the battery switch of the fire control panel.
Copyright © Huawei Technologies Co., Ltd.
4 Installation
86

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Luna2000-2.0mwh-2h0

Table of Contents